The following is an update about the Nebraska Department of Transportation's 23rd Street construction project.
Work from Last Week
• Paving: Mainline paving from near 1st Ave to East 6th Ave; various paving from 16th Avenue and 3rd Avenue.
• Electrical: Various work on conduits and structures for signal and light poles from 14th to East 11th.
• Underdrains: Finish underdrains east of East 6th Ave and from west of 3rd Avenue to 1st St.
Work Anticipated This Week
• Paving: Pour turn lanes at East 3rd Ave and East 6th Ave (eastbound), pour East 11th Avenue, sidewalk, inlet throats, and driveways.
• Electrical: Various work on conduits and structures for signal and light poles from 10th Avenue to East 3rd Avenue
• Underdrains: Finish underdrains east of East 6th Ave and along mainline pavement from west of 3rd Avenue to East 6th Avenue
Work Anticipated Next Week
• Underdrains: Construct underdrains along right turn lanes at East 3rd and East 6th Avenue
• Paving: Pour driveways, sidewalk, inlet throats, and median surfacing.
• Electrical: Various work on conduits and structures for signal and light poles from 3rd Avenue to East 6th.
Next Major Milestone
• Switch traffic to eastbound and westbound lanes in Segment 1 (East of 16th Avenue to east of East 11th Avenue). Traffic to be reduced to one lane in each direction, tentatively scheduled for the week of Nov. 20, 2023.