Posted on: November 15, 2023

NDOT provides update on 23rd Street construction project

23RDSTREET

The following is an update about the Nebraska Department of Transportation's 23rd Street construction project.

Work from Last Week

• Paving: Mainline paving from near 1st Ave to East 6th Ave; various paving from 16th Avenue and 3rd Avenue.

• Electrical: Various work on conduits and structures for signal and light poles from 14th to East 11th.

• Underdrains: Finish underdrains east of East 6th Ave and from west of 3rd Avenue to 1st St.

Work Anticipated This Week

• Paving: Pour turn lanes at East 3rd Ave and East 6th Ave (eastbound), pour East 11th Avenue, sidewalk, inlet throats, and driveways.

• Electrical: Various work on conduits and structures for signal and light poles from 10th Avenue to East 3rd Avenue

• Underdrains: Finish underdrains east of East 6th Ave and along mainline pavement from west of 3rd Avenue to East 6th Avenue

Work Anticipated Next Week

• Underdrains: Construct underdrains along right turn lanes at East 3rd and East 6th Avenue

• Paving: Pour driveways, sidewalk, inlet throats, and median surfacing.

• Electrical: Various work on conduits and structures for signal and light poles from 3rd Avenue to East 6th.

Next Major Milestone

• Switch traffic to eastbound and westbound lanes in Segment 1 (East of 16th Avenue to east of East 11th Avenue). Traffic to be reduced to one lane in each direction, tentatively scheduled for the week of Nov. 20, 2023.

Facebook Twitter Email

Other News in Columbus News

HYDRANT FLUSHING

Fall hydrant flushing coming up next week

Posted on: September 18, 2023
Bandshell

Frankfort Square band shell spray painted

Posted on: September 12, 2023
City of Power and Progress.png

NOTICE OF PUBLIC HEARING

Posted on: August 25, 2023